Friday, October 8, 2010

Construction update - end of week #3

Things are moving along well, this was a slower week because a few things are waiting on other things...but so far all the roof is framed, AC and electrical is done (and passed inspection) and the framing for the hallway extension is done. Next week we'll be doing insulation, roofing, our third inspection and if things go well the drywalling will start. Our new window and door should be here as well so they can finish the framing in our existing room (move the existing windows). Here are some pics of our old room / new hallway: